The Story So far..............
Scout Hut - September 2007

Funds raised to enable main structure to be built - 2009

Site Clearance & 100te sub base laid across site - October 2009
All The Portal Frame Concrete Pad Installed
November 2009
Main Structural Building Work Commences 7th December 2009
Cutting the Sod - December 2009
At the Scout Hut with our Christingles - 13th December 2009
Strip foundations installed - 19th December 2009
Inner roof sheet installed on North Side and Blocking to floor level - 30th January 2010
Inner roof sheet installed on both sides and blockwork to GL (including inner walls). 4th February 2010
Drains installed to sewer and soakaway. All inner walls double blocked. 14th February 2010
Inner walls filled with concrete, all roof on, netting down and facia board installed 21st February 2010
JCB filling in access ramp to enable hardcore base and concrete deliveries - 28th February 2010
Hardcore compacted, guttering installed and pea gravel laid around drains 8th March 2010