11th Workington (Harrington) Scout Group
 

The Story So far.............. 

                                                   Scout Hut - September 2007                              

Funds raised to enable main structure to be built - 2009

                     

   Site Clearance & 100te sub base laid across site - October 2009 

All The Portal Frame Concrete Pad Installed
November 2009
 

Main Structural Building Work Commences 7th December 2009




Cutting the Sod - December 2009

At the Scout Hut with our Christingles - 13th December 2009

Strip foundations installed - 19th December 2009

Inner roof sheet installed on North Side and Blocking to floor level - 30th January 2010

Inner roof sheet installed on both sides and blockwork to GL (including inner walls). 4th February 2010

Drains installed to sewer and soakaway. All inner walls double blocked. 14th February 2010

Inner walls filled with concrete, all roof on, netting down and facia board installed 21st February 2010

JCB filling in access ramp to enable hardcore base and concrete deliveries - 28th February 2010

Hardcore compacted, guttering installed and pea gravel laid around drains 8th March 2010